Invitation to BID

Package No. Particulars Contract Duration Approved Budget for Contract
2023
REGIONAL OFFICE
LMC No. 2023-01 CONSTRUCTION OF MULTI-PURPOSE BUILDING 240 Calendar Days 8,737,864.08
LMC No. 2023-02 LUPON IS: Construction of Irrigation Facilities 300 Calendar Days 65,930,775.45
LMC No. 2023-03 LASANG RIS: Completion of Diversion Dam and Construction of Downstream Protection Dike (Right Bank) from Sta. 0+036.50 to Sta. 0+076.00 300 Calendar Days 37,690,279.23
LMC-G No. 2023-01 SAUG RIS: Upgrading and Automation of 1 unit sluice gate, 4 units of intake gate and lifting mechanism 200 Calendar Days 35,620,911.32
LMC No. 2023-04 MANAT NIP (Package 2): Canalization of Left Main Canal with its Appurtenant structures (Sta. 0+000 – 2+890) 240 Calendar Days 49,169,315.16
LMC No. 2023-05 MIRAL SRIS: Installation of 23 units solar powered pumps on the existing/proposed dug wells 180 Calendar Days 37,546,218.04
LMC No. 2023-06 Improvement and Construction of Protection Works at Diversion Canal Sta. 1+754 to Sta. 2+161 and Sta. 2+443 - 2+650; Embankment, Construction and Compaction at Main Canal East Sta. 4+398 5+400 and Main Canal West Sta. 0+047 - 2+215 - SAUG RIS 360 Calendar Days 94,495,208.22
LMC No. 2023-07 Improvement and Construction of Protection Works at right side downstrream dam Sta. 0+000 - 0+287; Embankment Construction and Compaction at Lateral D6 Sta. 3+200 - 5+555 and Improvement of Main Canal Sta. 4+670 - 9+273 - LIBUGANON RIS 360 Calendar Days 94,471,071.25
LMC No. 2023-08 Channel Excavation of Lasang RIS and Construction of Downstream Protection Dike Sta. 0+076 - 0+206 300 Calendar Days 94,516,930.85
LMC No. 2023-09 Construction of Protection Dike at Upstream of Parat Dam along sta. 0+096.54 - 0+203.34 (left and right side) 210 Calendar Days 33,142,945.93
REGIONAL OFFICE CONSULTING
CS-FS No. 2023-01 Feasibility Study on National Irrigation Projects (NIP) of Liloan River - Taocanga NIP 360 Calendar Days 11,000,000.00
DAVAO del NORTE (2023)
DDN-LMC-2023-01 Concreting of Service Road along Lateral C -East at Sta. 2+000  to Sta. 2+457 SAUG RIS 120 calendar days 4,813,307.52
DDN-LMC-2023-02 Concreting of Service Road along Lateral D4 at Sta. 0+000  to Sta. 0+420 and from Sta. 0+700 to Sta. 0+804 LIBUGANON RIS 120 calendar days 4,815,668.28
DDN-LMC-2023-03 Concreting of Service Road along Lateral K at Sta. 0+000  to Sta. 0+484 LIBUGANON RIS 120 calendar days 4,812,460.27
DDN-LMC-2023-05 Concreting of Service Road along Lateral D -West at Sta. 0+074  to Sta. 0+532 SAUG RIS 120 calendar days 4,805,506.07
DDN-LMC-2023-06 Concreting of Service Road along Lateral A-1 at Sta. 0+000  to Sta. 0+477 LASANG RIS 120 calendar days 4,808,383.60
DDN-LMC-2023-07 Concreting of Existing Earth Canal Lining at Lateral A Sta. 0+000  to Sta. 0+728.09 ANAMAN CIS 210 calendar days 4,750,329.80
DDN-LMC-2023-08 Installation of 2 units Steelgates at Inlet Structures, installation of 79 lengths of 10" dia. HDPE pipe SDR 11 at main canal, construction of 1,819.63m concrete canal lining at main canal and construction of 5 units canal structure at main canal - Palma Gil SPIP 210 calendar days 11,050,138.36
DDN-GDSI-2023-07 Supply, Delivery and Installation of Smart Discharge at Main Canal Sta. 0+150 LASANG RIS 120 calendar days 9,614,984.07
DDN-GDSI-2023-08 Supply, Delivery and Installation of Smart Discharge at Main Canal Sta. 0+200 LIBUGANON LEFT RIS 120 calendar days 9,623,035.47
DDN-LMC-2023-04 Concreting of Service Road along Lateral B LIBUGANON LEFT RIS 120 calendar days 4,814,612.77
DDN-LMC-2023-09 Concreting of Existing Earth Canal Lining at Lateral A and Lateral B and its Appurtenant Canal structures SEMONG CIS 300 calendar days 9,502,556.93
DDN-LMC-2023-10 Repair of Damaged Portion of Canal and Canal Structures and Concreting of Existing Earth Canal at Main Canal Right - LIMBAAN CIS 300 calendar days 9,467,905.74
DDN-LMC-2023-11 Concreting of Main Canal West, Lateral D West and Supply, Delivery and Installation of 15 units Steel Gates - SAUG RIS 360 calendar days 19.897.309.97
DDN-LMC-2023-12 Concreting of Lateral A West Canal, Lateral B West and Construction of Protection Dike Station - SAUG RIS 360 calendar days 19,627,249.50
DDN-LMC-2023-13 Construction of 1 Unit Solar Pump and Restoration of Area at Main Canal at Sta. 1+232 and Canalization of Lateral A1 - LIBUGANON LEFT RIS 360 calendar days 11,359,616.51
DDN-LMC-2023-14 For Improvement of Lateral A Canal and Lateral H Canal - LIBUGANON RIS 120 calendar days 2,863,183.54
DDN-LMC-2023-15 For Improvement of Lateral B, F and D6 Canal and Supply, delivery and installment of steel gates - LIBUGANON RIS 120 calendar days 19,250,906.18
DDN GDSI 2023-25 Construction of Multi-Purpose Building (MITAMUNDO INDIGENOUS PEOPLE COUNCIL SLEEPING QUARTERS) - Upper Saug RIP 120 calendar days 1,864,944.00
DDN GDSI 2023-40 Procurement of Survey Instrument (RTK for MIDP Project) 90 calendar days 2,200,000.00
DAVAO de ORO (2023)
LMC No. DDO 2023-001 Construction of 128 m Protection Dike and Slope Protection of Canal Structures; Repair and Rehabilitation of Canal Structures at Tagbibinta CIS 180 calendar days 4,742,083.76
LMC No. DDO 2023-002 Repair of Dam Trash Rack at Hijo River and Construction of Protection Dike: 140 m at Dapon Area and 9.6 m Limbo Area, Nuevo Iloco CIS 240 calendar days 7,576,388.87
LMC No. DDO 2023-003 Rehabilitation of Steel Gates, Repair of Intake and 59.55 m Protection Dike and Construction of Manhole at Closed Conduit, Trash Rack, Tower Shed and 1.72-km Access Road at Lower Naboc CIS 180 calendar days 4,745,586.89
LMC No. DDO 2023-004

Repair of 138.90 m. Protection Dike at Cabidianan CIS

240 calendar days 7,581,339.83
LMC No. DDO 2023-005 Rehabilitation of Steel Gates, 40-m Canal Lining, and Canal Structure, and Construction of 224-m Protection Dike at Dauman CIS 240 calendar days 9,486,240.30
LMC No. DDO 2023-006 Repair of Trash Rack and Tower Shed at Tagmanok Dam, Lined Canal at Kinabalian Area, and Canal Structure at Magaad Area; Construction of Protection Dike: 66.5 m at Magaad Area and 60 m at Kinabalian Area at Kidawa CIS, 240 calendar days 7.593.969.16
LMC No. DDO 2023-007 Repair of Lined Canal and Canal Structure; Construction of Slope Protection of Lined Canal and Canal Structure at Haguimitan CIS, 90 calendar days 1,900,730.46
LMC No. DDO 2023-008 Repair of Dam Wasteway and Intake at Ulip River; Construction of 174.2-m Protection Dike at Salvacion-Union CIS 240 calendar days 7,581,732.69
LMC No. DDO 2023-009 Rehabilitation of Check Structure at Tadia Creek, Construction of New Intake, Manhole of Close Conduit 204m Concrete Planks, Repair of 20m Lined Canal, and Installation os Steel Gate with Trash Rack at Simsimin CIS 180 calendar days 4,742,952.65
LMC No. DDO 2023-010 Construction of 127.5m Protection Dike and Repair of 110m Concrete Canal at Batutu RIS 300 calendar days 23,661,715.97
LMC No. DDO 2023-011 Construction of 273.90m Protection Dike at Batutu RIS 240 calendar days 14,208,307.72
LMC No. DDO 2023-012 Rehabilitation of Diversion Dam, Installation of Steel Gates and Construction of 44m Protection Dike at San Miguel CIS 300 calendar days 23,859,781.90
LMC NO. DDO 2023-013 Construction and Installation of One (1) unit Sluice Gate and Four (4) units Intake Gate with Electrical Power Supply, AC Generator, Power House, Intake Shed, and Electrical Motor Control Units at Batutu RIS 305 calendar days 14,425,483.49
LMC NO. DDO 2023-014 Package 1: Construction of 1 unit Check structure at Agutayan Area, 3.12-km Concrete canal lining, 46 units Appurtenant Canal Structures and 1.17-km Access Road at Bongloy CIP 350 calendar days 15,759,667.55
LMC NO. DDO 2023-015 Package 2 : Construction of 1 unit Check Structures at Malokoloko Area, 1.45-km Concrete Canal Lining, 30 units Appurtenant Canal Structures and 1.02-km Access Road at Bongloy CIP 300 calendar days 12,023,053.55
LMC NO. DDO 2023-016 Package 1: Canalization of Right Main Canal with its Appurtenant structures
(Sta. 2+160 – 3+621.82) and Installation of HDPE Pipe at RMC Lateral C and D
at Manat NIP
304 calendar days 22,393,909.85
LMC NO. DDO 2023-017 Package 3: Canalization of Lateral A and B of Left Main Canal with its Appurtenant structures and Supply, Delivery, and Installation of HDPE Pipe and its accessories at Lateral B1 and B2 of LMC at Manat NIP 304 calendar days 29,506,584.41
LMC NO. DDO 2023-018 Package 4: Canalization of Left Main Canal Lateral D with its Appurtenant structures at Manat NIP 304 calendar days 16,252,427.03
POG NO. DDO 2023-CM-007 SUPPLY & DELIVERY OF HARDWARE AND CONSTRUCTION MATERIALS AT NIA IMO DDO FOR THE CONSTRUCTION OF MANAT NIP AT LMC LATERAL C (CY2023 FAW) IN THREE (3) PACKAGES 30 calendar days 5,648,540.00
POG NO. DDO 2023-CM-008 Supply, Delivery and installation with commissioning and river care of 1 unit sluice gate (2.5m x 2.0m) and 1 unit intake gate (1.50m x 0.84m) of AWAO CIS 90 calendar days 2,958,321.81
LMC NO. DDO 2023-019 Construction of 48 meter Afflux Dike at Left Side Upstream of Manat Dam at Manat NIP, Montevista, Davao de Oro 60 calendar days 5,494,959.08
DAVAO ORIENTAL (2023)
LMC No. DAVOR-2023-01 CONSTRUCTION OF PCCP SERVICE ROAD AT MAIN CANAL AND LATERAL A OF LUPON IS 120 calendar days 4,809,631.04
LMC No. DAVOR-2023-02 CONSTRUCTION OF PCCP SERVICE ROAD AT LATERAL C OF LUPON IS 120 calendar days 4,809,632.58
LMC No. DAVOR-2023-03 CONSTRUCTION OF IRRIGATION FACILITIES AT LUPON IS 330 calendar days 18,841,512.81
LMC No. DAVOR-2023-04 CONSTRUCTION OF IRRIGATION FACILITIES AT BAGANGA CIS, Baganga 150 calendar days 9,422,725.09
LMC No. DAVOR-2023-05 CONSTRUCTION OF IRRIGATION FACILITIES AT CABUYAWAN CIS 150 calendar days 5,655,403.12
LMC No. DAVOR-2023-06 CONSTRUCTION OF IRRIGATION FACILITIES AT KINABLANGAN CIS 180 calendar days 4,713,058.64
LMC No. DAVOR-2023-07 CONSTRUCTION OF IRRIGATION FACILITIES AT CARMEN CIS 180 calendar days. 5,655,232.49
LMC No. DAVOR-2023-08 CONSTRUCTION OF IRRIGATION FACILITIES AT CATEEL PIP 100 calendar days 3,538,021.20
LMC No. DAVOR-2023-09 CONSTRUCTION OF SOLAR-POWERED PUMP IRRIGATION AND PROJECT FACILITIES AT CATEEL PIP 300 calendar days 14,160,663.86
LMC No. DAVOR-2023-10 CONSTRUCTION OF IRRIGATION FACILITIES AT SAN PEDRO CIS 160 calendar days 3,771,226.64
LMC No. DAVOR-2023-11 CONSTRUCTION OF IRRIGATION FACILITIES AT MANORIGAO I CIS, 240 calendar days 22,258,454.10
LMC No. DAVOR-2023-13 CONSTRUCTION OF IRRIGATION FACILITIES AT BANAHAW SIS 75 calendar days 1,886,170.69
DAVAO DEL SUR (2023)
LMC-DS-2023-05 Construction of Irrigation Facilities of Balasiao CIS 90 Calendar Days 1,089,047.87
LMC-DS-2023-06 Construction of Irrigation Facilities of Cebuza SIS 150 Calendar Days 9,473,642.49
LMC-DS-2023-07 Construction of Irrigation Facilities of Bonifacio CIS 90 Calendar Days 3,046,122.07
LMC-DS-2023-08 Construction of Irrigation Facilities of Dakinus CIS 120 Calendar Days 7,578,870.53
LMC-DS-2023-09 Construction of Service Road of Padada RIS 150 Calendar Days 9,617,322.70
LMC-DS-2023-10 Construction of Service Road of Mal RIS 150 Calendar Days 7,694,796.51
LMC-DS-2023-11 Construction of Irrigation Facilities of Padada RIS 180 Calendar Days 14,277,059.11
LMC-DS-2023-13 Construction of Irrigation Facilities of Titugop SIS CY 2023 180 Calendar Days 9,222,558.22
LMC-DS-2023-15 Construction of Irrigation Facilities of Kawayan SIS CY 2023 90 Calendae Days 870,961.22
LMC-DS-2023-16 Construction of Irrigation Facilities of CARFA SIS CY 2023 90 Calendae Days 2,430,641.94
LMC-DS-2023-22 Construction of Irrigation Facilities of Balutakay CIS CY 2023 150 Calendae Days 3,789,521.10
LMC-DS-2023-14 Construction of Irrigation Facilities of Wangan SIS CY 2023 180 Calendae Days 6,427,006.31
LMC-DS-2023-19 Construction of Irrigation Facilities of Kilolog CIS CY 2023 120 Calendae Days 6,765,414.11
LMC-DS-2023-20 Construction of Irrigation Facilities of Mabini Barayong CIS CY 2023 180 Calendae Days 7,009,301.23
LMC-DS-2023-21 Construction of Irrigation Facilities of San Agustin CIS CY 2023 150 Calendae Days 3,789,772.98
LMC-DS-2023-27 Provision of Solar Powered Pump Irrigation and Appurtenant Irrigation Facilities of Mal RIS for CY 2023 180 Calendae Days 18,460,291.09
LMC-DS-2023-28 Construction of Irrigation Facilities of Mal RIS for CY 2023 180 Calendae Days 28,406,187.51
DS-G-2023-43 Supply and Delivery of One (1) Lot Hardware and Construction Materials of BANGKAL CIS 15 Calendar Days 1,499,393.00
DS-G-2023-44 Supply and Delivery of One (1) Lot Hardware and Construction Materials of UNIFARM CIS 15 Calendar Days 1,288,170.00
DS-G-2023-69 Supply and Delivery of Pre-Mix Concrete for Padada RIS Service Road CY 2020-Revised 3 20 Calendar Days 916,234.62
DS-G-2023-70 Supply and Delivery of Pre-Mix Concrete for Padada RIS Service Road CY 2021-Revised 4 40 Calendar Days 2,305,525.17
DS-G-2023-71 Supply and Delivery of Pre-Mix Concrete for Mal RIS Service Road CY 2021-Revised 4 30 Calendar Days 1,727,898.99
LMC-DS-2023-72 Construction of Irrigation Facilities of Mamacao CIS CY 2023 180 Calendar Days 23,674,190.45
LMC-DS-2023-73 Construction of Irrigation Facilities of CARFA SIS CY 2023 180 Calendar Days 23,673,944.74
LMC-DS-2023-74 Construction of Irrigation Facilities of Wangan SIS CY 2023 180 Calendar Days 9,471,467.60
LMC-DS-2023-79 Supply and Delivery of One (1) Lot Hardware and Construction Materials of Tanwalang SIP CY 2022 15 Calendar Days 1,726,550.00
LMC-DS-2023-102 Construction of Greenhouse Structure with Drip Irrigation Powered by Solar System 90 Calendar Days 1,300,000.00
LMC-DS-2023-108 Construction of Protection Dike of Sampaguita CIS CY 2023 90 Calendar Days 3,848,392.05
DS-Auction-01-2023 Sale of ONE (1) LOT UNSERVICEABLE EQUIPMENT September 25-27, 2023 165,914.57
 
2024
DAVAO DEL SUR (2024)
LMC-DS-2024-01 Construction of Protection Dike and Retaining Wall of Sampaguita CIS CY 2024 180 Calendar Days 23,670,872.63
LMC-DS-2024-02 Construction of Service Road of Mal RIS CY 2024 90 Calendar Days 4,809,615.88
LMC-DS-2024-03 Construction of Service Road of Padada RIS CY 2024 90 Calendar Days 4,809,655.14
LMC-DS-2024-04 Repair of Dilapidated Irrigation Canal and Canal Structure of Mal RIS CY 2024 250 Calendar Days 14,033,866.35
LMC-DS-2024-05 Repair/Rehabilitation of Trapezoidal Canal Lining and Canal Structure of Padada RIS CY 2024 270 Calendar Days 14,206,377.87
LMC-DS-2024-06 Rehabilitation of the existing Diversion Dam of Padada CIS CY 2024 210 Calendar Days 18,938,666.58
LMC-DS-2024-07 Repair/Rehabilitation of Existing Diversion Dam of San Isidro CIS CY 2024 180 Calendar Days 13,864,498.03
LMC-DS-2024-08 Modification of Intake Structure of Suawan-Tamugan SIP Cy 2024 180 Calendar Days 7,599,075.00
LMC-DS-2024-09 Installation of HDPE Pipe of Dakinus CIS CY 2024 120 Calendar Days 5,071,122.80
LMC-DS-2024-10 Construction of Irrigation Facilities of Little Baguio SIS CY 2024 110 Calendar Days 1,437,970.21
LMC-DS-2024-11 Installation and Construction of Solar Powered Pump and Installation of HDPE Pipe of Kisulan SPIP CY 2024 240 Calendar Days 26,734,205.71
LMC-DS-2024-12 Construction of Irrigation Facilities and Installation of HDPE Pipe of Bolo-bolo SIP CY 2024 180 Calendar Days 8,733,294.70
REGIONAL OFFICE XI (2024)
LMC No. 2024-01 SAUG RIS: Construction of Protection Works at Downstream Dam (Left and Right Side) from Sta. 0+000 to Sta. 0+152 330 Calendar Days 96,605,058.73
LMC No. 2024-02 LIBUGANON RIS: Construction of Protection Works at Barobo Drainage junction Lateral D Series from Sta. 1+349 to 2+280 330 Calendar Days 96,592,082.84
LMC No. 2024-03 LASANG RIS: Construction of Protection Works at Lasang Downstream Dam (Left Side) at Sta. 0+100.45 to Sta. 0+212.60 330 Calendar Days 96,184,888.07
LMC No. 2024-04 UPPER SAUG RIP: Construction of Slope Protection Works of the Diversion Dam, Main Canal from Sta. 14+509.92 - Sta. 16+476.69, Lateral F from Sta. 0+000 - Sta. 2+034, Lateral G from Sta. 0+812.17 - Sta. 1+706.18, Improvement of Main Drainage and Construction of its Appurtenant Structures and Road Surfacing 360 Calendar Days 78,343,238.39
LMC No. 2024-05 MANAT NIP (Package 1): Canalization of RMC with its Appurtenant Structures (3+621.82 - 4+740.00) and Installation of HDPE Pipe at RMC (4+740.00 -5+125.40) and RMC Lateral E 240 Calendar Days 15,709,370.92
LMC No. 2024-06 MANAT NIP (Package 2): Canalization of LMC with its Appurtenant Structures (2+890.00 - 3+900.00) 240 Calendar Days 18,131,583.02
LMC No. 2024-07 MANAT NIP (Package 3): Canalization of LMC Lateral C and C-1 with its Appurtenant Structures 240 Calendar Days 29,536,614.93
LMC No. 2024-08 MANAT NIP (Package 4): Supply, Delivery, and Installation of HDPE PIPE (SDR 11) at LMC Lateral D-1 and D-2  240 Calendar Days 15,453,275.47
LMC No. 2024-09 MANAT NIP (Package 5): Supply, Delivery, Installation and Commissioning of Steel Gates Automation 300 Calendar Days 47,996,303.67
LMC No. 2024-10 Construction and Improvement of Irrigation Facilities (Cateel IIS) 270 Calendar Days 86,659,808.70
LMC No. 2024-11

Construction of Irrigation Facilities (Installation of Solar Panel - Libuganon River-Katipunan SPIP

240 Calendar Days 67,878,808.29
LMC No. 2024-12

Installation of Solar Powered Pump and Construction of Irrigation Facilities

240 Calendar Days 96,851,600.83
LMC No. 2024-13 Construction of Protection Works at Barobo Drainage Junaction Lateral D-Series from Sta. 0+000 - Sta. 1+348.20 and Lateral D-Series Sta. 0+780 to 1+665.40 - Libuganon RIS 180 Calendar Days 241,865,510.02
LMC No. 2024-14 Construction of 400 meters Protection Dike Upstream of Batutu Dam at Brgy. Cogonon and 300 meters River Dredging along Batutu River 180 Calendar Days 97,000,896.10
LMC No. 2024-15 Construction of Protection Works at Diversion Canal (Left and Right Side) from Sta. 0+000 to Sta. 0+813.20 Asuncion, Davao del Norte 180 Calendar Days 193,440,489.92
LMC No. 2024-16 Construction of 393 meter Protection Dike (Lateral A-1 East Area) along the Right Bank of Batutu RIS 184 Calendar Days 97,001,138.14
DAVAO DEL NORTE (2024)
DDN LMC No. 2024-01 Concreting of Service Road Along Lateral D-4 at Sta. 0+825.50 to Sta. 1+061.50 (Libuganon RIS) 120 calendar days 2,868,272.64
DDN LMC No. 2024-02 Concreting of Service Road Along Lateral D-1 at Sta. 0+352 to Sta. 0+806.50 (Libuganon RIS) 120 calendar days 5,765,279.62
DDN LMC No. 2024-03 Concreting of Service Road Along Lateral C-EAST at Sta. 1+738.50 to Sta. 1+961.50 (Saug RIS) 120 calendar days 2,862,964.91
DDN LMC No. 2024-04 Concreting of Canal at Lateral D-8 Sta. 1+814.25 to Sta. 2+161.19 and Sta. 2+172.80 to Sta. 2+368.80 (Libuganon RIS) 330 calendar days 7,582,541.22
DDN LMC No. 2024-05 Concreting of Canal at Lateral D-5 Sta. 0+000 to Sta. 0+054.75, Sta. 0+059.54 to Sta. 0+257.21 and Sta. 0+266.34 to 0+594.84 (Libuganon RIS) 330 calendar days 7,579,694.30
DDN LMC No. 2024-06 Concreting of Canal at Lateral D-4 Sta. 2+276.29 to Sta. 2+771.59 (Libuganon RIS) 330 calendar days 4,738,806.40
DDN LMC No. 2024-07 Concreting of Canal at Lateral G Sta. 0+807.50 to Sta. 1+630.00 (Libuganon RIS) 330 calendar days 7,582,263.09
DDN LMC No. 2024-08 Concreting of Canal at Lateral D-4 Sta. 0+000 to Sta. 0+757.19 (Libuganon RIS) 330 calendar days 7,971,283.77
DDN LMC No. 2024-09 Concreting of Canal at Lateral B West Sta. 0+000 to Sta. 0+043.95 and Sta. 0+047.47 to 0+236.47 (Saug RIS) 330 calendar days 7,581,581.47
DDN LMC No. 2024-10 Concreting of Canal at Main Canal Sta. 1+709.37 to Sta. 1+843.39, Sta. 2+202.39 to Sta. 2+263.82, Sta. 3+539.25 to Sta. 3+583.70, Sta. 3+585.14 to Sta. 3+635.16 and Sta. 3+635.16 to Sta. 3+825.86 (Gabuyan RIS) 330 calendar days 4,736,394.46
DDN LMC No. 2024-11 Concreting of Canal at Lateral K-1 Sta. 0+523.10 to Sta. 0+711.09, Sta. 0+719.29 to Sta. 0+851.79, Sta. 0+860 to Sta. 0+987.61 and Sta. 0+995.81 to Sta. 1+132.81 (Libuganon RIS) 330 calendar days 7,584,255.46
DDN LMC No. 2024-12 Concreting of Service Road Along Lateral D Sta. 0+580.00 to Sta. 0+795.00 (Libuganon Left RIS) 120 calendar days 2,861,009.81
DDN LMC No. 2024-13 Concreting of Lateral B Caal Sta. 0+310 to Sta.0+909.44, Construction of Irrigation Structures and Diversion Damm Foor Bridge - (Bunawan Kipalili CIS)) 240 calendar days 4,751,989.16
DDN LMC No. 2024-14 Construction of Irrigation Facilities (Installation of Solar Panel) (Upper Palma GIL SPIP) 300 calendar days 28,909,025.58
DDN LMC No. 2024-15 Emergency repair of the damages cause by Heavy Flooding Embankment, Construction and Compaction of Anibongan Creek (Sta. 1+597 to Sta. 4+098) - Libuganon RIS 300 calendar days 29,943,797.12
DDN LMC No. 2024-16 Concreting of Main Canal from Sta. 3+945 - Sta. 4+326.65 and at Sta. 18+520 to Sta. 19+483.93, Lat B-1 from Sta. 2+123.48 to Sta. 2+588.97, Lat. B-2 from Sta. 0+306.28 to Sta. 0+804.81, Lat B from Sta. 7+981.06 to Sta. 9+530, Repair of Main Canal - Drainage Box Culvert at Sta. 3+450 and Drainage 60 End structure at Sta. 0+000 - LASANG RIS 300 calendar days 38,019,658.40
DDN GDSI 2024-08 Procurement of Construction Materials for the Construction of Irrigation Canal thru Force Account Works - Upper Saug RIP 90 calendar days 4,307,700.07
DDN LMC No. 2024-17 Improvement of Canal (Main Canal East) - SAUG RIS 240 calendar days 19,024,253.04
DDN LMC No. 2024-18 Improvement of Drainages (Densio, Morit and Magdagondong) 240 calendar days 9,405,542.44
DDN LMC No. 2024-19 Emergency Repair of Irrigation Facilities Embankment, Construction and Compaction of Lateral B West and Lateral B-1 West - SAUG RIS 290 calendar days 28,212,034.45
DDN LMC No. 2024-1-20 Remove and Replace of Cp-4 Type Lifting Mechanism Intake Steel Gates at LASANG RIS 120 calendar days 1,922,126.56
DDN LMC No. 2024-21 Remove and Replace of 12 units Steel Gates at Main Canal, 2 units Steel Gates at Lateral D-2 and 1 unit Steel Gate at Lateral D-Series (from Tandem Type to Single Pedestal) - LIBUGANON RIS. 150 calendar days 15,376,425.73
DDN GDSI 2024-22 Procurement of Construction Materials for the partial renovation of Proposed Engineering Office (Formerly Lasang RIS Office) 90 calendar days 2,190,890.80
DAVAO ORIENTAL (2024)
LMC No. DAVOR-2024-01 Construction of PCCP Service Road at Main Canal and Lateral A of Lupon IS, Banay-banay, Davao Oriental 75 calendar days 2,405,603.07
LMC No. DAVOR-2024-02 Construction of PCCP Service Road at Lateral C and Lateral C-1 of Lupon IS, Lupon, Davao Oriental 75 calendar days 2,405,599.82
LMC No. DAVOR-2024-03 Construction of Irrigation Facilities at Lupon IS, Lupon, Davao Oriental 300 calendar days 28,262,259.29
LMC No. DAVOR-2024-04 Rehabilitation of Diversion Dam and Repair of Irrigation Facilities, Luzon SIS, Davao Oriental 120 calendar days 9,421,999.00
LMC No. DAVOR-2024-05

Construction of Irrigation Facilities at Olin SIS, Baganga, Davao Oriental

135 calendar days 3,771,119.90
LMC No. DAVOR-2024-06 Construction of Irrigation Facilities at Masao SIS, Baganga, Davao Oriental 105 calendar days 3,741,000.27
DAVAO DE ORO (2024)
LMC NO. DDO 2024-002 Repair of Dam Sluice Steel Gate; Construction of 78.40- m Protection Dike at Station 0+033.00 to Station 0+111.40 Upstream of Dam Leftside, Nabunturan, Davao de Oro 180 calendar days 4,740,734.86
LMC NO. DDO 2024-003 Construction of 74-meter protection dike L/R Upstream of Samuag Creek Check structure 1 Salvacion-Union CIS, Monkayo, Davao de Oro 180 calendar days 4,737,369.45
LMC NO. DDO 2024-004 Construction of 470.55-m Lined canal along Lateral B; Construction of 22-m Left Side upstream and 23-m at Right side downstream protection dike, Upper Saosao, Mawab, Davao de Oro 180 calendar days 4,738,818.22
POG NO. DDO 2024-CM-001 Supply and Delivery of Hardware and Construction Materials at NIA IMO DDO for the Repair of Damaged Irrigation Canal at Lateral C West from Sta. 0+000 to Sta. 1+386.50 with Canal Structures at Batutu RIS in Four (4) Packages 30 calendar days 3,876,074.25
POG NO. DDO 2024-CM-002 Supply and Delivery of Hardware and Construction Materials at NIA IMO DDO for Concreting of Service Road along Main Canal East 446m. length at Batutu RIS in three packages. 30 calendar days 1,674,471.75
POG NO. DDO 2024-CM-003 Supply and Delivery of Hardware and Construction Materials at NIA IMO DDO for the construction of Manat NIP at LMC Lateral E (1+120 - 2+773.40) 30 calendar days 7,213,387.63